Bone Bank Archaeological Research

Posey County, Indiana



Rescue Excavations at the Bone Bank Archaeological Site in Southwestern Indiana

Introduction Indiana's First Archaeological Excavation Survey and Testing Significance Project Goals Research Stages Expected Results Bone Bank in 2000 Planning for 2001 Current Work In the News Fall 2001 Lecture References Geomorphological History Links



August 29 to September 2, 2001

After excavation blocks and trenches were layed out according to grid, we used a backhoe to remove plow disturbed soils and recent alluvium that comprise level 1. In Block 2, a laser level (loaned to the project by Indiana State University, Department of Anthropology) was used to guide the mechanical excavation to the target elevation for the base of 1 (106.3 m ASL). As expected, the tree stumps and roots certainly made excavation difficult, but there were far more stumps present than were visible on the ground surface!!!

A backhoe removing soil while two people guide the mechanical excavation




FOREGROUND: Following mechanical excavation, the loose dirt in Block 2 was removed by hand excavation. Then the mud that followed a 2-inch downpour was allowed to dry. Mississippian midden deposits are present just below the base of the excavation at elevation 106.3.
BACKGROUND: At Block 1 on higher ground, we began shovel scraping the base of excavation units to search for pit and wall trench features that intrude the subsoil. Portable canopy-type tents (loaned by the Paul Weimer family) made this hot, hard work considerably easier.

Block 2 in foreground, and Block 1 on higher ground in the background




Block 2: Initial layout of excavation units within a 2 x 10 m area. Strings mark the sides of Units 4A-4J and 4K-4T. Nails with pink tape mark the corners of the units.

Block 2: Initial layout of excavation units within a 2 x 10 m area. Strings mark the sides of Units 4A-4J and 4K-4T. Nails with pink tape mark the corners of the units.






Previous Weeks
First Week (August 22-26, 2001)
Second Week (August 29 - September 2, 2001)
Third Week (September 5 - September 9, 2001)
Fourth Week (September 12 - September 16, 2001)
Fifth Week (September 19 - September 23, 2001)
Sixth Week (September 26 - September 30, 2001)
October (October 1 - October 26, 2001) Part 1
October (October 1 - October 26, 2001) Part 2
Thanks Everyone!
Current Week


Return to Top

Last updated on 9/17/2001

Send Comments to: munsonc@indiana.edu

Site sponsored by Indiana University